What is dirección de ejecución de obra?
Dirección de ejecución de obra directs material execution and checks the construction and built quality both qualitatively and quantitatively. The director de la ejecución belongs to the professional supervision team. Article 13 of Spain’s LOE defines the duties for works within its scope.
Duties and responsibilities
Check product reception
Verify reception of construction products and order the necessary tests. Keep batch references, received documentation and results linked to the relevant work sections.
Direct material execution
Check setting out, materials, execution and installation of elements and services against the design and director de obra’s instructions. Record the actual scope of each check.
Record instructions and follow-up
Enter necessary instructions in the Libro de Órdenes y Asistencias. Track issues with location, evidence and verified status; a photo or contractor’s message alone does not verify an item.
Contribute to project records
Sign the setting-out or start record and completion certificate; prepare and sign interim certificates and the final account as specified by the LOE. Contribute control results to the as-built documentation.
Site supervision and execution supervision: differences
Focus
Site supervisionDevelopment of the works in accordance with the design.
Execution supervisionMaterial execution and qualitative and quantitative control.
Checks
Site supervisionSetting out and suitability of foundations and structure for the ground.
Execution supervisionSetting out, materials, execution and element placement.
Records
Site supervisionInstructions, design changes and as-built documentation.
Execution supervisionInstructions, product controls, tests and results.
Relationship
Site supervisionDuties under LOE article 12.
Execution supervisionDuties under article 13, coordinated with the director de obra.
What to check and document on each visit
- Review work in progress and the controls planned for that stage.
- Link received products, batches, documents and tests to their use location.
- Identify the drawing and revision used when checking axes, levels or element placement.
- Photograph relevant elements before they are concealed, without replacing necessary testing.
- Distinguish a reported issue, a reported fix and an actually verified fix.
- Update owners, deadlines and item history, then share reviewed minutes.
Example: from a requested test to a traceable result
When requesting a concrete test, identify the element, date and sample reference. Record the request, then the received result and competent assessment. Do not mark a control compliant simply because the laboratory has announced that a report will be sent.
Which record to use at each project stage
The PDF is a site visit record.
Frequently asked questions
How does execution supervision differ from dirección de obra?
Must execution supervision always be performed by an arquitecto técnico?
Who signs a setting-out record in Spanish building works?
Is a snagging record a completion certificate?
Official sources
- BOE · LOE, article 13: director de la ejecución
- BOE · LOE, article 12: director de obra
- BOE · LOE, article 6: reception of works
Informational guide to building works in Spain covered by the LOE. Check the appointment, professional qualifications and rules applying to your case. This is not a substitute for professional advice.